Brentwood 278 Works

We've successfully wrapped up the 278 works project in Brentwood ahead of our tight deadline - just in time for the schools to return in September 2025.
Year:2025
Key Features:Our team delivered everything on scope: Council works licence obtained, Zebra crossing removal completed, 4 Belisha beacons disconnected, 580m2 of Tarmac footpaths laid. All kerbs replaced: 1220m2 of 100mm highway resurfacing with 68PSV HRA surface course, White lining finished, New toucan crossing and traffic lights installed and operational